The Japanese in Burma are now compelled to resort increasingly to
delaying tactics. In this connection, the first two bridge demolitions
of any importance performed by Japanese forces in this theater are of
interest. These were partial demolitions, and showed signs of
defective technique. One bridge was built of masonry and is
referred to in this article as Bridge A. The other bridge, referred
to as Bridge B, was of steel-girder construction. Both bridges had
been designed to carry a narrow-gauge railway.
TWO-SPAN MASONRY BRIDGE
Bridge A (see fig. la) was a two-span, masonry bridge, which had
one span of 15 feet and one span of 40 feet. The two spans, or
arches, each 4 bricks thick, were supported at the center
by a masonry pier rising from the watercourse below. The
Japanese demolished only the 40-foot span, leaving intact
the two bridge-end abutments, a pier between the spans, and
the 15-foot span.
After examining the bridge, military observers report that six
pressure demolition charges probably were employed by the
Japanese to destroy the long span. The condition of the arch
stumps and the nature of the debris indicate that two charges
were placed near the abutment, two at the span's center, and two
close to the pier. That charges were placed at the span's center
may be deduced from the fact that most of the rubble under the
bridge was in comparatively small pieces. If no center charge
had been used, the debris would have contained larger chunks.
|
Figure 1a. Bridge A. The 40-ft masonry arch was destroyed, but the
short span, the center pier, and the two bridge-end abutments were left
intact. Figure 1b. Bridge B. The far I-beam (65 ft.) was damaged by a
charge which blew out approximately 16 ft. of its vertical section. This
beam buckled, but remained in place. One end of the near beam was
forced from the abutment and slid down the hillside; its pier end remained
in place. |
TWO-SPAN STEEL-GIRDER BRIDGE
Bridge B (see fig. 1b) contained two steel-girder spans, each
65 feet long. Each span consisted of two steel I-beams, 4 inches
deep and with horizontal members 15 inches wide. At the center of
the bridge, the two spans rested on a high masonry pier. Only one
span was demolished by the Japanese. The second span, the center
pier, and the two abutments were left intact.
This demolition (according to the observers) was
effected in a rather unusual manner. Charges were so
placed on the span that portions of the vertical panels
in both I-beams were blown out, but the upper and
lower horizontal members of the beams remained intact.
Furthermore, charges were not placed in the
same relative positions on the two beams. One beam,
with approximately 16 feet of its vertical panel destroyed,
merely buckled and remained in position. The
other beam was damaged by a charge which blew out
a few feet of the vertical section next to the abutment.
The end of the beam was forced off the abutment and
slid several feet down the hillside, while the end resting
on the pier remained in place.
The technique employed by the Japanese in these
demolitions was poor. Subsequently, both bridges were
reconstructed by British engineers, who were able to
utilize the piers and other elements of the bridges left
standing by the enemy. According to an observer,
"Bridge A could have been rendered far more useless
if the pier had been destroyed and one or both abutments
partially destroyed. If a demolition charge had
been placed near the top of the center pier of Bridge B, the
entire bridge would have collapsed and the obstacle
would have been more formidable. The comparative
ineffectiveness of the demolitions probably was the
result of inexperience and improper appreciation of
demolition technique."